INTERCHANGE AT INTERSECTION OF HIGHWAY NO.41 AND 403 (THUNG SONG)
NAKHON SI THAMMARAT

Client :
Department of Highways

Designed By :
Department of Highways

Constructed By :
Christiani & Nielsen (Thai) PCL

Overview :
Construction of Highway Interchange project. Scope of work comprise of
– To upgrade existing & new road – 2 layer 5 cm. asphaltic concrete surface with
shoulder.
– New P.C. Bridges (Box girder type, roadway 8.0 m.) with bridge approach
structure – 2 locations, total length 1,552.472 m.
– New bridge over railway (Box girder type, roadway 20.00 m.) with bridge
approach structure – 1 location, length 172 m.
– New U-Turn bridge (Box girder type, roadway 6.00 m.) with bridge approach
structure – 1 location, length 280 m.
– New R.C. Bridges (Roadway width 8.0 – 11.00 m.) – 3 locations
– Widening of existing bridges – 3 locations
– Underpass, Roadway 5.90 m. – 1 location, length 265 m.
– New pedestrain bridge – 3 locations
– Other involved M&E works and other road incidental works.